    Four consecutive tender cancellations have held up the full commissioning of the Colombo Port’s East Container Terminal (ECT), with the Government now making a fifth attempt to procure 15 straddle carriers even as it explores handing over operations of the State-owned facility to a private operator.

    With 82–85% of civil construction completed, the terminal faces a further wait of 10–12 months for the equipment to arrive after the contract is awarded, raising questions over repeated procurement failures at one of Sri Lanka’s key port development projects.

    Speaking to The Sunday Morning, Ports and Civil Aviation Minister Anura Karunathilaka revealed that four previous tenders for straddle carriers had been cancelled for different reasons, while the fifth procurement process was nearing completion following negotiations with two bidders.

    “The main issue is the procurement of equipment, particularly straddle carriers,” the Minister said.

    He said that the Government expected to conclude negotiations and award the contract within approximately two months, particularly as the validity period of the current bids was approaching its expiry.

    “We expect to complete the process within this year. The bid validity period is also approaching its end. Therefore, we need to complete the negotiations and award the contract within approximately the next two months,” he explained.

    However, even if the contract is awarded within the anticipated time frame, the terminal will not be immediately ready for full operations.

    “After awarding the contract, it will take another 10–12 months for the equipment to be delivered and become operational,” the Minister said.

    - https://www.themorning.lk/articles/tjXnS9M7t8DEoVhFYNNi
     
    • Like
    Reactions: CohenLenstra

    Anyhacker

    Well-known member
  • Oct 5, 2026
    2,288
    1,152
    113
    United States
    ටෙන්ඩර් 4ක්ම කැන්සල් වෙලා පස්වෙනි එකටත් තව මාස 10-12ක් යනවා කියන්නෙ වැඩේ තවත් පරක්කු වෙනවා තමයි. 85%ක් හදලා ඉවර ටර්මිනල් එකක් මෙහෙම හිරවෙලා තියෙන එක නම් හරිම අපරාධයක්
     
    • Haha
    Reactions: elajani

    tharakaf

    Well-known member
  • Oct 19, 2020
    37,544
    77,885
    113
    Four consecutive tender cancellations have held up the full commissioning of the Colombo Port’s East Container Terminal (ECT), with the Government now making a fifth attempt to procure 15 straddle carriers even as it explores handing over operations of the State-owned facility to a private operator.

    With 82–85% of civil construction completed, the terminal faces a further wait of 10–12 months for the equipment to arrive after the contract is awarded, raising questions over repeated procurement failures at one of Sri Lanka’s key port development projects.

    Speaking to The Sunday Morning, Ports and Civil Aviation Minister Anura Karunathilaka revealed that four previous tenders for straddle carriers had been cancelled for different reasons, while the fifth procurement process was nearing completion following negotiations with two bidders.

    “The main issue is the procurement of equipment, particularly straddle carriers,” the Minister said.

    He said that the Government expected to conclude negotiations and award the contract within approximately two months, particularly as the validity period of the current bids was approaching its expiry.

    “We expect to complete the process within this year. The bid validity period is also approaching its end. Therefore, we need to complete the negotiations and award the contract within approximately the next two months,” he explained.

    However, even if the contract is awarded within the anticipated time frame, the terminal will not be immediately ready for full operations.

    “After awarding the contract, it will take another 10–12 months for the equipment to be delivered and become operational,” the Minister said.

    - https://www.themorning.lk/articles/tjXnS9M7t8DEoVhFYNNi
    @handley පොශ් ඩෝබියෝ, මේකත් රනිල්ගෙ හොර/පාඩු ඩීල් එකක්ද?

    @redux එලුවගේ පස්සෙ දුවලා ඉවර උනාම ඇවිත් මේකටත් මොනාහරි කියන් පලයන් 🤭 🤭
     

    redux

    Well-known member
  • Feb 19, 2017
    11,282
    18,585
    113
    හානේ ඇයි මේ යන්නේ. මේ කොම්පැනි වලට කවුරුහරි තේරුන් කරලා දීපන්කො රනිල් ල මහින්දලා බංකොලොත් කරපු රටක invest කරන එකෙන් කොච්චර ප්‍රතිලාබ ලැබෙනවද කියල

    @handley පොශ් ඩෝබියෝ, මේකත් රනිල්ගෙ හොර/පාඩු ඩීල් එකක්ද?

    @redux එලුවගේ පස්සෙ දුවලා ඉවර උනාම ඇවිත් මේකටත් මොනාහරි කියන් පලයන් 🤭 🤭
    පොඩ්ඩක් ඉන්න අකිලගේ ෂෙඩ් එකක නවත්තලා තෙල් ගහන ගමන් ඉක්මනට එන්නන්
    ------ Post added on Oct 18, 2026 at 2:25 PM
     
    • Haha
    Reactions: mall_9n

    Clockwork

    Well-known member
  • Mar 6, 2024
    10,066
    9,620
    113
    හානේ ඇයි මේ යන්නේ. මේ කොම්පැනි වලට කවුරුහරි තේරුන් කරලා දීපන්කො රනිල් ල මහින්දලා බංකොලොත් කරපු රටක invest කරන එකෙන් කොච්චර ප්‍රතිලාබ ලැබෙනවද කියල


    පොඩ්ඩක් ඉන්න අකිලගේ ෂෙඩ් එකක නවත්තලා තෙල් ගහන ගමන් ඉක්මනට එන්නන්
    ------ Post added on Oct 18, 2026 at 2:25 PM
    @monson akilage thel karayonta government pension ekakk hambenawa kiyanne aththada
     
    • Haha
    Reactions: redux