    China projects steam ahead

    Monday, 20 August 2018

    image_be9197f34e.jpg


    • Chinese companies confident of completing railway extension and fourth phase of highway by Jan.
    • Project includes longest railway bridge and railway, funded by $ 278 m loan from China EXIM Bank
    • Highway connecting Mattala Airport and H’tota Port also nearing end, 75% completed
    • Rest of $ 1.9 b Southern Highway to be completed in 3Q of 2019, Kottawa-Kataragama in three and a half hours
    • H’tota Port operations expand in 1Q, project 85% y-on-y growth, targets 20 m TEUs by 2040

    By Maleesha Sulthanagoda

    China is confident of completing their multiple investments in southern Sri Lanka with the fourth phase of the highway from Mattala Airport to the Hambantota Port and the Matara-Beliatta railway extension likely to be completed by January 2019, top officials said.



    The railway project, funded by a $ 278 million loan from China EXIM Bank, is being built by the China National Machinery Import and Export Corporation (CMC). CMC Senior Consultant Engineer Pathmasiri Hallowita told reporters engaged in an observation visit organised by the Chinese embassy last week that they had completed 90% of the work on the 26.75 km long extension from Matara to Beliatta.



    “This is one of the most technologically advanced railway lines in Sri Lanka. The construction work on the Kekunadura Railway station is near completion. It is a dual-floored station building that contains quarters for the staff. This is also connected to a supermarket for the convenience of the travellers. This is the most modern railway line in Sri Lanka where a train can operate at a speed limit of 120 kmph, and operations are slated to commence in four to five months,” he said.



    About 1,500 local workers and about 300 Chinese workers engaged in the construction of the railway extension project. He also added that the final stage of the first phase will include main railway stations in Kekunadura, Bambarenda, Wewrukannala and Beliatta. It was also said that there will also be two substations along the new railway extension.



    Officials from the construction company also mentioned that the longest railway bridge in Sri Lanka was being constructed at Wattegama, which is 1.5 km in length, and the longest railway was also built at Nakutiya at 616 m in length as a result of this project.



    The fourth phase of the Southern Highway, which is a stretch of 23 km, connects Mattala Airport with the Hambantota Port. Built at a cost of $ 6.23 million, the section is also expected to be completed by 19 January 2019. The rest of the phases, which is Matara to Beliatta at 30 km, Beliatta to Wetiya at 26 km and the third section from Wetiya to Andarawewa at 15 km, are also targeted to be completed after September 2019. Officials noted that delays in the construction were largely due to complications linked to land acquisition with as many as 50 families needing to be relocated.



    “The length of the fourth section is 23 km. In the original plan it was 25 km, but later we reduced it to 23 km as the road to the airport was in good condition. We have completed more than 75% of the work. About 80% of the material used in the construction is from Sri Lankan suppliers,” Southern Highway extension Section Four Project Director A.P.K. Abeydeera.



    When the full $ 1.9 billion project is completed, people will be able to travel from Kottawa to Kataragama in three and a half hours, officials said. The fourth phase is being constructed by China Communication Constructions, with consultation from the China Harbour Engineering Company and funding from China Exim Bank.



    The Hambantota Port was also seeing progress with increases in its operations. The Hambantota International Port (HIP) handled 106,135 vehicles and 153 ships in the first half of 2018, when compared with the 109,716 vehicles handled in 2017, a top official of the Hambantota International Ports Group said on Friday.



    HIPG Chief Operating Officer Tissa Wickramasinghe said that the Roll-on Roll-off (RORO) volumes handed by the HIP had increased during the past two years.



    “Operations at HIP commenced with RORO and will continue to develop in a phased format. RORO volumes have increased over the years. In the first half of 2018, HIP handled 106,135 vehicles and 153 ships, while in 2017 we only handled 109,716 vehicles. We project a year-on-year growth of 85%,” he said.



    He went on to reveal the projected growth of the port for the future and their future plans for the port.



    “HIP was developed as a multi-purpose port. It was designed to handle Roll-on Roll-off (RORO), passengers, oil, bulk cargo, gas, project cargo and for container handling. The HIP was built to handle a gamut of services in the maritime and logistics area. The feasibility studies done before the construction of the port also showed that bulk cargo would constitute the main traffic to the port until 2030, and it also highlights that the port would be able to handle 20 million TEUs by 2040,” he added.

    - http://www.ft.lk/top-story/China-projects-steam-ahead/26-661222
     

    monson

    Well-known member
  • May 7, 2007
    25,519
    28,327
    113
    Fairway enters Kurunegala

    image_a804013e9a.jpg


    Fairway Holdings’ second venture out of Colombo was inaugurated with the ground-breaking ceremony for ‘Fairway Kurunegala’, a proposed mixed development building project, which took place on 16 August at the picturesque project site in Kurunegala, the capital of the North Western Province. The Chief Guest for the ceremony was Minister of Megapolis and Western Development Patali Champika Ranawaka. The Guest of Honour was Mayor of Kurunegala Municipal Council Thusara Sanjeewa Witharana.


    Fairway Holding’s entry into Kurunegala is in recognition of the city’s established importance as a major city in Sri Lanka and a vibrant regional business hub. A focal point in both the Central Expressway and the railway running from Colombo to the North, the city is a thriving wholesale and retail centre and contains a number of popular schools.

    The proposed building, which will potentially be a landmark in Kurunegala, has been conceptualised and designed by senior architect Mohan Silva with maximum emphasis being given to comfort, safety and state-of-the-art conveniences. 75% of the building’s space will contain 180 luxury apartments, including four penthouses, and the balance 25% will contain a shopping mall with leading local and international brands, offices, a food court and beer garden, a supermarket and ample commercial parking. The use of environmentally friendly material for construction will ensure sustainability and longevity.

    - http://www.ft.lk/propertyconstruction/Fairway-enters-Kurunegala/10516-661181
     

    monson

    Well-known member
  • May 7, 2007
    25,519
    28,327
    113
    diyunu ratakin genawa kiyala jame beraganna americawen wisik karana petti kattakui , ituru okkoma india and china walin geneida :rolleyes:

    6 Diesel-Electric Multiple Units from India(ICF)
    9 Diesel-Electric Multiple Units from China(Dong Feng Co.)

    12 Engines from USA(Generel Electric)
    10 Engines from India(Rites)
    4 Engines from China(Dong Feng Co.) for Aruwakkalu Waste Project

    160 compartments from India

    30 oil tankers
    20 container carrier wagons to transport coal and flour
    34 container carrier wagons for Aruwakkalu Waste Project


    Major investment to upgrade railway system

    By Damith Wickremasekara

    Sri Lanka is making a major investment in upgrading its railway system by importing new engines and wagons from Chinese and US companies, according to a top official. Sri Lanka Railways General Manager S.M. Abeywickreme said a Chinese company had been awarded a contract for US$ 80 million (Rs 12 billion) to deliver nine multiple units, each comprising an engine and eight to nine compartments with air-conditioning facilities. The compartments would have monitors displaying the next station and the time to reach the next destination.

    The delivery is expected by November this year.
    The engines and compartments will have a two-year warranty for mechanical parts and five year warrant for electrical parts. The Chinese company was selected by a worldwide tender.

    The Railways Chief said a second contract to buy 12 engines, each of them costing more than US$ 4 million, would be awarded to a US company. The project would cost about US$ 48 million (Rs seven billion). The delivery of the engines is expected within a year.

    He said these purchases were in addition to the purchase of six power sets, 10 engines, 30 oil tankers and 20 container type wagons to transport coal and flour and 160 compartments under a Indian credit line costing US$ 105 million (Rs 15.7 billion).
    The delivery of the engines and wagons is expected within this year.


    - http://www.sundaytimes.lk/180114/news/major-investment-to-upgrade-railway-system-277301.html
     
    Last edited:

    monson

    Well-known member
  • May 7, 2007
    25,519
    28,327
    113
    ADB - Sri Lanka: Country Operations Business Plan (2019–2021)

    Transport

    Integrated Road Investment Program tranche 5 is reduced from $193
    million to $150 million.
    Colombo Suburban Railway Efficiency Improvement Project amount
    is increased from $100 million to $150 million and moved from 2018
    to 2019 program.

    Second Transport Project Preparatory Facility in 2019 is dropped.
    Colombo Suburban Railway Investment Program is advanced to
    2020 firm program and renamed as Kelani Valley Railway Investment
    Program (phase 1).

    Second Integrated Road Investment Program tranche 3 amount is
    reduced from $200 million to $100 million.
    Four new projects added: Integrated Road Investment Program
    (tranche 6) for $93 million in 2020; SASEC Port and Logistics
    Development Project for $200 million in 2021; Sri Lanka Railway
    Investment Program (tranche 2) for $200 million in 2021; and Second
    Integrated Road Investment Program (tranche 4) for $200 million in
    2021.

    Energy

    Strengthening Power System Stability, Reliability and Protection
    Project is renamed Power System Reliability Strengthening Project
    and moved from 2019 to 2020.
    Distribution Automation and Metering Project is moved from 2020 to
    2021.


    Agriculture, Natural Resources, and Rural Development

    Northern Province Sustainable Fisheries Development Project
    regular OCR amount is increased from $60 million to $111 million;
    the concessional OCR funding will be signed in 2018 and OCR
    funding in 2019.
    Technical assistance to conduct an assessment on the existing
    lagoons is added to 2019 program for $500,000.

    Mahaweli Water Security Investment Program tranche 3 is moved
    from 2019 to 2020 and increased from $143.8 million to
    $173.8 million.
    Agribusiness Value Chain Development Project in 2020 program is
    replaced with Integrated Water Productivity Improvement Project in
    2020 program for $170 million.

    Water and Other Urban Infrastructure and Services

    Greater Colombo Wastewater Management Project (additional
    financing) is dropped from the pipeline.
    A multitranche facility for Integrated Water Supply Investment
    Program originally proposed for 2020 is converted to a stand-alone
    project for 2020.
    Secondary Towns Sustainable Development Project for $180 million
    is included in 2021 program.

    Education

    Second Education Sector Development Project is advanced to 2019.
    Technical assistance to prepare Second Education Sector
    Development Project is renamed Support for Human Capital
    Development Initiative.
    Innovation Capacity Development in Higher Education Project for
    $100 million is included in 2021 program.

    Finance

    Tea Sector Capital Expenditure Finance Project for $100 million is
    added in 2019 pipeline.

    - https://www.adb.org/documents/sri-lanka-country-operations-business-plan-2019-2021
     

    monson

    Well-known member
  • May 7, 2007
    25,519
    28,327
    113
    රැකියා විරහිත උපාධිධරයෝ 4100කට පත්වීම් ලබති
    (නිමල කොඩිතුවක්කු)

    රැකියා විරහිත උපාධිධාරින් 4100ක් සඳහා පත්විම් ලිපි ප‍්‍රදානය අග්‍රාමාත්‍ය රනිල් වික‍්‍රමසිංහ මහතාගේ ප‍්‍රදානත්වයෙන් අරලියගහ මන්දිරයේ දී අද (20) සිදුකෙරිණි.

    ස්වදේශ කටයුතු අමාත්‍යාංශය, ව්‍යාපෘති කළමනාකරණ සහ යෞවන කටයුතු අමාත්‍යංශය ඇතුළු අමාත්‍යාංශ සඳහා එම පිරිස අනුයුක්ත කර තිබේ.

    වත්මන් ජාතික රජය බලයට පත්ව 2017 වර්ෂය අවසන් වනවිට සෘජුව ලියාපදිංචි කළ සේවා නියුක්තිකයන්ගේ සංඛ්‍යාව හාර ලක්ෂ තිස්දහසක් බව අග‍්‍රාමාත්‍ය රනිල් වික‍්‍රමසිංහ මහතා එහිදි පැවසීය.

    මෙම කාළය තුළ ස්වයං රැකියා , විදේශ රැකියා ආදි සියල්ල එක් කළ විට ලක්ෂ හතකට පමණ රැකියා, ආදායම් මාර්ග ඇතිකර ඇති බවද අග‍්‍රාමාත්‍යවරයා එහිදි වැඩිදුරටතත් සඳහන් කළේය.

    මෙම අවස්ථාව සඳහා තරුණ කටයුතු, ව්‍යාපෘති කළමනාකරණ හා දක්ෂිණ සංවර්ධන අමාත්‍ය සාගල රත්නායක, ස්වදේශ කටයුතු අමාත්‍ය වජිර අබේවර්ධන, ජාතික ප‍්‍රතිපත්ති හා ආර්තික කටයුතු රාජ්‍ය අමාත්‍ය නිරෝෂණ පෙරේරා, පාර්ලිමේන්තු මන්ත‍්‍රීවරුන් වන කාවින්ද ජයවර්ධන, හේෂා විතානගේ යන මහත්වරුන් සහ අමාත්‍යාංශ ලේකම්වරුන් ඇතුළු පිරිසක් එක්ව සිටියහ.