මේ වෙනකොට ගල් අඟුරු නැව් 18ක් එන්න ඕනේ ඇවිල්ලා තියෙන්නේ 11
ඊයෙත් 165MW ක් අඩුයි.
- https://cebcare.ceb.lk/gensum/details
Sri Lanka needs 1.5 million tons of coal this year. That means 25 ships of 60,000 tons each will arrive.
The Indian company that supplied the inferior coal had bid $98.5 per ton. The second lowest company bid $100. That is $1.5 less per ton. A profit of $2.25 million will be made from 1.5 million tons.
But since this supplier supplied inferior coal and did not send the ships on time, a tender was issued to transport 05 ships under separate hadith purchases. The ton cost $142. The country lost $42 per ton. The country lost $12.6 million per 3 million tons. Minister gave the tender to a corrupt company that only considered the lowest price and even brought inferior rice in the past.
These losses will ultimately be borne by the people of the country.
ඊයෙත් 165MW ක් අඩුයි.
- https://cebcare.ceb.lk/gensum/details
Sri Lanka needs 1.5 million tons of coal this year. That means 25 ships of 60,000 tons each will arrive.
The Indian company that supplied the inferior coal had bid $98.5 per ton. The second lowest company bid $100. That is $1.5 less per ton. A profit of $2.25 million will be made from 1.5 million tons.
But since this supplier supplied inferior coal and did not send the ships on time, a tender was issued to transport 05 ships under separate hadith purchases. The ton cost $142. The country lost $42 per ton. The country lost $12.6 million per 3 million tons. Minister gave the tender to a corrupt company that only considered the lowest price and even brought inferior rice in the past.
These losses will ultimately be borne by the people of the country.