House construction - Labour rates

aluthKolla0001

Active member
  • Dec 27, 2015
    709
    63
    28
    colombo
    Machanla, me dawaswala gewal hadana ape kollongen loku udawwak ona machan. Ubala gedara costruction karaddi contract dunna aya poddak ubala dunna labour rates tika kotagena yamda bro,
    Meka ape godak denekta sehenna wedagath wei kiyala hithuwa bonsai mehema ahuwe.
    Jayawewa!!
     

    surarocks

    Active member
  • Apr 17, 2008
    694
    176
    43
    Foundation ekata

    01. Base wala kalapa, Net dala, 11 feet walata - 8000.00 (wala natuwa 6500.00)

    02. Foundation eka kapala badinna, gal cube ekakata 7500.00 (Api kapala dunnoth 6500.00)

    03. Block galak badinna 35.00

    04. Linton 1 feet - 70

    Mama me rates gatte last week .... matanam penne wadie wage....
     

    aluthKolla0001

    Active member
  • Dec 27, 2015
    709
    63
    28
    colombo
    Foundation ekata

    01. Base wala kalapa, Net dala, 11 feet walata - 8000.00 (wala natuwa 6500.00)

    02. Foundation eka kapala badinna, gal cube ekakata 7500.00 (Api kapala dunnoth 6500.00)

    03. Block galak badinna 35.00

    04. Linton 1 feet - 70

    Mama me rates gatte last week .... matanam penne wadie wage....

    Colums walata ehema rates gaththe nedda machan. Base wala 11feet danawada bn?
     

    Ozone4

    Well-known member
  • Aug 26, 2016
    3,756
    6,016
    113
    No Where
    Contract deepan. measure & pay. :yes:

    (per 1 sq.ft)
    Plaster - Rs.30.00
    Beam/column plaster - Rs.45.00
    Putty - Rs.25.00
    Block Work - Rs.45.00
    Floor Conc - Rs.35.00
     

    aluthKolla0001

    Active member
  • Dec 27, 2015
    709
    63
    28
    colombo
    Contract deepan. measure & pay. :yes:

    (per 1 sq.ft)
    Plaster - Rs.30.00
    Beam/column plaster - Rs.45.00
    Putty - Rs.25.00
    Block Work - Rs.45.00
    Floor Conc - Rs.35.00

    Ow machan mamath contract denna inne.eth unge rates gena tikak compare karala balana eka katath honda nisai machan mehema ahuweth
     

    sachee1986

    Member
    Nov 22, 2011
    3
    0
    1
    Ground floor

    Block bricks 35 per brick
    Kaparalu 35 per sqft
    Column 250 per dik adi
    concrete for floor 35 sqft (Not for slab)
    Complete the bathroom 35000-45000 depend on the bathroom size
    lintol 120 per dik adi
    uluvahu fixing per uluvahu 2000
    Paint poti with two paint coat 25 per SQft
    Paint without poti 15 per sqft

    Those prices are i have taken 2 months ago this price was little bit high but based on these prices you can get some ideas
     

    sachee1986

    Member
    Nov 22, 2011
    3
    0
    1
    Tile 45 per sqft
    skerting 30 for dik adi
    Pantry slab with complete the Pantry 25000
    actually my Ground floor has 1200 sqft i expense 37 lakh
    and my first floor construction now ongoing it has 1400 sqft including finish asbestos roof i will be expense nearly43 lakh this is for your information only