Building The Hoover Dam...

Chami_Boy

Member
Jul 6, 2015
671
288
0
1931-1936​
Building the Hoover Dam​

hooverdam-53.jpg
c. 1935
Officials ride in one of the penstock pipes of the soon-to-be-completed Hoover Dam.







In the early years of the 20th century, the rapid development of the southwestern United States was creating a high demand for electricity and water. Simultaneously, a series of catastrophic floods made it clear that the Colorado River needed to be dammed and controlled.

In 1922, the U.S. Reclamation Service settled on Black Canyon as the ideal location for a dam. They had initially chosen Boulder Canyon (unfortunately located on a seismic fault line), which gave the project its first name, Boulder Dam.

Congress authorized the project in 1928; construction began in 1931, under the direction of a consortium called Six Companies, Incorporated.
The Great Depression was in full swing, and tens of thousands of hopeful workers flocked to the dam site with their families, camping out in temperatures that reached 120 degrees Fahrenheit. At its peak, the project employed 5,251 people.







hooverdam-50.jpg
c. 1928
An inspection party near the proposed site of the dam in the Black Canyon on the Colorado River.







hooverdam-18.jpg
c. 1932
A surveyor signals to colleagues during the construction of the dam.






hooverdam-1.jpg
May 12, 1933
Four tons of dynamite are detonated in the canyon in the early stages of construction.






The first step: diverting the river away from the construction site. Three miles of diversion tunnels were dug on both sides of the river, and huge berms or “cofferdams" were built above and below the site.

With the riverbed dry, excavation began. Millions of tons of loose sediment and rocks were scraped away to reveal bedrock. The design called for an arch-gravity dam, which would transfer the crushing force of the water reservoir to the abutting canyon walls.

To make sure those walls were solid, workers known as “high scalers” had to rappel down them, hammering away anything loose. Falling rocks were a serious hazard, so the workers dipped their hats in tar and let them dry and harden — the first hard hats.





hooverdam-5.jpg
1933




hooverdam-6.jpg

1933




hooverdam-7.jpg

1933




hooverdam-40.jpg

c. 1935
"High scalers" use jackhammers to shave loose rock off the walls of Black Canyon.






hooverdam-33.jpg
1934
"High scalers" rappel down the canyon wall.






In June 1933, the pouring of the concrete began. The chemical reactions which occur during the hardening of concrete generate high levels of heat. Engineers estimated that if the entire dam had been poured as a single concrete block, it would have taken 125 years to cool (and it would have collapsed).

To circumvent this problem, the concrete was poured into discrete rectangular plots called “lifts.” It was then cooled with pipes filled with ice-cold water. By the time the pouring ceased in May 1935, approximately 3.25 million cubic yards of concrete had been used — enough to pave a highway from New York to San Francisco.

Though the myth that there are bodies entombed in the dam is just that, a myth, there were officially 112 deaths as a result of the project. The first was J. G. Tierney, a surveyor who drowned while searching for a spot for the dam on December 20, 1922. The last worker to die on the dam lost his life 13 years to the day later — Tierney’s son, Patrick.





hooverdam-34.jpg
Sept. 11, 1933
The concrete foundation of the dam is poured into separate blocks called "lifts."





hooverdam-51.jpg
1934




hooverdam-25.jpg
1934
A bucket holding 18 tons of concrete is maneuvered into position.





hooverdam-19.jpg
1934
Concrete is dropped into place.






hooverdam-38.jpg
Sept. 19, 1933




hooverdam-8.jpg
1934





hooverdam-9.jpg
c. 1934
The base of one of the intake towers under construction.





hooverdam-24.jpg


hooverdam-23.jpg
1934




hooverdam-10.jpg
c. 1934




hooverdam-17.jpg



hooverdam-32.jpg

1934




hooverdam-39.jpg
Jan. 30, 1935
Student engineers stand atop one of the 2 million-pound hydroelectric generators for the dam at the General Electric factory in Schenectady, New York.






hooverdam-12.jpg
Feb. 25, 1935
Construction on the dam proceeded day and night.





hooverdam-14.jpg
1936
Workers apply a coat of paint to one of the dam's spillways.





hooverdam-41.jpg
October 1935
The dam nears completion.






hooverdam-52.jpg





On Sept. 30, 1935, President Franklin D. Roosevelt stopped by the dam for a formal dedication ceremony. A year later, the hydroelectric power plant was finally turned on, providing electricity to cities in California, Nevada and Arizona.

Eventually renamed Hoover Dam in 1947, the dam was the largest manmade structure in the world when completed, and created Lake Mead, the largest reservoir in the United States.






hooverdam-44.jpg
c. 1935
President Franklin D. Roosevelt tours the dam.






hooverdam-4.jpg
Sept. 11, 1936





hooverdam-36.jpg
1940