[FONT="]Case-1 – Earned Value Management[/FONT]
[FONT="]You have undertaken a project to build a large stainless steel box. The box is six sided. Each side is to take one day to build and is budgeted for $1000 per side. The sides are planned to be completed one after the other. Today is the end of day three.[/FONT]
[FONT="]Below is a status chart produced by your team leader in charge of this project.[/FONT]
[FONT="]Task[/FONT]
[FONT="]Progress[/FONT]
[FONT="]Cost spent[/FONT]
[FONT="]Side 1[/FONT]
[FONT="]||||||||||||||||||||||||||||||||||||||||100%[/FONT]
[FONT="]$1,200 [/FONT]
[FONT="]Side 2[/FONT]
[FONT="]||||||||||||||||||||||||||||||||||||||||100%[/FONT]
[FONT="]$1,000 [/FONT]
[FONT="]Side 3[/FONT]
[FONT="]||||||||||||||||||||||||||||||75%[/FONT]
[FONT="]$750 [/FONT]
[FONT="]Side 4[/FONT]
[FONT="]||||||||||||||||||||50%[/FONT]
[FONT="]$500 [/FONT]
[FONT="]Side 5[/FONT]
[FONT="]0%[/FONT]
[FONT="]$0 [/FONT]
[FONT="]Side 6[/FONT]
[FONT="]0%[/FONT]
[FONT="]$0 [/FONT]
menna me ගාන හදන්න දන්න කෙනෙක් සිටීද ?