ස්ලැබ් එකට යන cost එක

Jul 3, 2012
1,394
116
0
ස්ලැබ් එකට යන cost එක

මචන්ල 350 sqft වගේ පොඩි slab එකකට ගල්,වැලි,සිමෙන්ති,යකඩ වගේ materials වලට යන cost එකයි,labor cost එක වගේ විස්තරයි කාටද දෙන්න පුලුවන් :)
 

solopiz

Well-known member
  • Jun 7, 2013
    1,183
    155
    63
    mehema ganan hadala balapna square feet akakta Rs. 480 gane dala balapan. mata bas kenek dunne ganan ohomai.
     

    Dr. COCO

    Member
    Sep 12, 2009
    1,164
    194
    0
    මචන්ල 350 sqft වගේ පොඩි slab එකකට ගල්,වැලි,සිමෙන්ති,යකඩ වගේ materials වලට යන cost එකයි,labor cost එක වගේ විස්තරයි කාටද දෙන්න පුලුවන් :)


    Toilet eke pol athu wahalaya wenuwata concrete daanna wage yanne. :P:P:P ela ela. mekata thamai AASHCHARYA kiyanne:lol::lol::lol::lol::lol:
     

    Heshankavindu

    Active member
  • Jan 25, 2009
    995
    59
    28
    ape adi 700kata giya bass kulith ekka full coste eka(satalim lali walata gahana ane idan bass kuliya wenakan) 4lakhs mita aurudu 2kata wage kalin
     

    Leesha

    Member
    Dec 12, 2010
    12
    2
    0
    uba use karanne Grade 20 concrete nam (1:2:4);

    uba deela thiyana details anuwa ubata 1.4 Cube withara yanawa concrete ekata.

    Cement (50kg) = 27
    Sand = 0.7 Cube
    Metal (3/4) = 1.33 Cube
    Water = 120 Galoons


    r/f detail kiyanne steel bars gena thiyana details. Oya materials wala prices uba hoyagena deela thiyana quantities walin wadi karapan.

    Labour cost ekka ubata roughly 35,000-45,000 athara ganak yai concrete walata. ( Kambi walata amathrawa)
     
    Last edited:

    shamrincool

    Well-known member
  • Jan 6, 2011
    1,189
    65
    48
    uba use karanne Grade 25 concrete nam (1:2:4);

    uba deela thiyana details anuwa ubata 1.4 Cube withara yanawa concrete ekata.

    Cement (50kg) = 27
    Sand = 0.7 Cube
    Metal (3/4) = 1.33 Cube
    Water = 120 Galoons


    r/f detail kiyanne steel bars gena thiyana details. Oya materials wala prices uba hoyagena deela thiyana quantities walin wadi karapan.

    Labour cost ekka ubata roughly 35,000-45,000 athara ganak yai concrete walata. ( Kambi walata amathrawa)

    grade 25 kiyanne 1:2:4 nemei bn! ehema thibbata 2kama wenas minum 25 weight 1ta hada ganne anik eka pari mawata. asanna washayen samanai unata wenas bn! ade cube 4k witara ona wena wane bn! 350 sqft 5"
     